Saturday, 24 June 2017

Tribal Houses In Wayanad District

Government have issued sanction for the construction of 270 buildings for Primitive Tribes at Sulthan Bathery Taluk in Wayanad District as a part of construction of housing schemes for the primitive tribes during the year 2006-2007 vide order GO No. 420/2006/SCSTDD dated 26.05.2006. The work has been entrusted with KSHB as decided in the meeting conducted by Wayanad District Collector on 08.01.2007.  Accordingly the Executive Engineer, Wayanad Division has been entered into Agreement with the Tribal Department on 05.02.2007.   The construction of cost of one building is Rs. 90,000/- and the total cost required for the construction of 270 buildings amounts to Rs. 243 lakhs and the amount has been received from ST Department.

Out of the 270 buildings started construction, 270 buildings in the following Panchayath have been completed in all respect as on 30/09/2009,   and handed over to tribal department.

Sl No Name Of Panchayath No Of Houses Constructed
1 Ambalavayal 17
2 Meenangadi 26
3 Mullan Kolli 26
4 Nenmeni 18
5 Nool Puza 55
6 Poothadi 58
7 Pulppally 34
8 Sulthan Bathery 36
Total 270

 

 

 